RACI Matrix
A grid that clarifies who is responsible, accountable, consulted and informed for each task or decision.
What it is
A RACI matrix lists tasks down one side and people or roles across the top. Each cell holds a letter showing that person's part in the task.
Its purpose is to remove ambiguity: every task has exactly one accountable owner, and nobody is surprised by a decision they expected to be asked about.
When to use it
At the start of a project, after a reorganization, or whenever work is falling between teams or decisions are being made twice.
The four roles
- Responsible Does the work. There can be more than one.Ask: Who does the work?
- Accountable Owns the outcome and signs off. Exactly one per task.Ask: Who signs off, and is it only one person?
- Consulted Gives input before the work or decision; communication is two-way.Ask: Whose input is needed first?
- Informed Kept up to date on progress or the result; communication is one-way.Ask: Who needs to know afterwards?
Example
For a product launch, the product manager is accountable for pricing, finance is responsible for the pricing model, sales is consulted, and customer support is informed. A dispute over who approves discounts is settled by reading the chart.
How to run it
- List tasks down the side and people across the top.
- Assign R, A, C or I for each task.
- Check every task has exactly one A.
- Agree it with the team and keep it current.
Limits
It can become a bureaucratic exercise, and too many people marked as consulted slows everything down. It records roles but does not resolve disagreements about them.