The theory of constraints holds that the output of any system is set by its weakest link. Effort spent improving anything other than the constraint does not increase output and may just build up inventory.

Management attention should therefore go to finding the constraint and organizing everything else around it.

01When to use it

When a process has a bottleneck, when local efficiency improvements are not raising overall output, or when work in progress keeps piling up.

02The five focusing steps

5
  1. 1Identify the constraint
    Find the step that limits the output of the whole system.
  2. 2Exploit the constraint
    Get the most from it with what you have; never let it sit idle.
  3. 3Subordinate everything else
    Pace other steps to the constraint rather than running them flat out.
  4. 4Elevate the constraint
    If more is still needed, add capacity there.
  5. 5Repeat
    When the constraint moves, start again.

03Example

A plant finds that a heat-treatment oven limits total output. It schedules the oven through breaks, inspects parts before they reach it so it never processes defects, and slows upstream machines to match. Output rises without new equipment.

04Limits

Finding the true constraint can be hard, especially when it is a policy or the market rather than a machine. It suits processes with a clear flow better than complex knowledge work.

05Where it comes from

Eliyahu Goldratt introduced it in his 1984 novel The Goal.